Const. of Parsuram Bhawan in Barona in Panchayati land
Community Buildings
Haryana / SONIPAT — SONIPAT(DEPUTY COMMISSIONER SONEPAT_IDA) · Satpal Brahamchari (SONEPAT)
Overall risk score
45/100
Blended from the five components below, each weighted as shown.
Risk components
Cost60
Delay100
Duplication0
Agency31
Compliance0
Sanctioned
₹10.00 L
Delay
180d
Cost deviation
60%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹1,000,000 against a ₹625,250 median for Community Buildings works in SONIPAT (60% above, 54 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 180 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.