Construction of bus stand in jagaluru city
Community Buildings
Karnataka / DAVANAGERE — Davanagere(DEPUTY COMMISSIONER DAUANAGERE_IDA) · Prabha Mallikarjun (DAVANAGERE)
Overall risk score
54/100
Blended from the five components below, each weighted as shown.
Risk components
Cost55
Delay100
Duplication0
Agency100
Compliance0
Sanctioned
₹12.00 L
Delay
195d
Cost deviation
55%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹1,200,000 against a ₹774,556 median for Community Buildings works in DAVANAGERE (55% above, 69 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 195 days beyond expected completionPublished dates
- 98% of this agency's ₹58,186,763 spend went to one vendor (NIRMITHI KENDRA DAVANGERE), across 3 vendors and 93 transactionsStatistics · Herfindahl-Hirschman index
Decision trail
Nobody has recorded a decision on this work yet.