Construction of room and retrieval facility for Saraswati Sh

Education

Uttar Pradesh / BASTI — BASTI(DISTRICT MAGISTRATE BASTI_IDA) · Ram Prasad Chaudhary (BASTI)

Construction of room and retrieval facility for Saraswati Shiksha Niketan Science Academy, Kamharia Sapaha, Block-Bahadurpur, District Basti

Overall risk score
65/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost100
Delay100
Duplication0
Agency100
Compliance0
Sanctioned
₹25.00 L
Delay
196d
Cost deviation
213%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹2,500,000 against a ₹800,000 median for Education works in BASTI (212% above, 13 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 196 days beyond expected completionPublished dates
  • 81% of this agency's ₹148,929,312 spend went to one vendor (JAI CONSTRUCTION), across 17 vendors and 241 transactionsStatistics · Herfindahl-Hirschman index

Decision trail

Nobody has recorded a decision on this work yet.