Development of Urinal and Latrine at Garakhiya Gohai Than at

Drainage & Sanitation

Assam / BARPETA — BARPETA(DEPUTY COMMISSIONER BARPETA 1) · Phani Bhusan Choudhury (BARPETA)

Development of Urinal and Latrine at Garakhiya Gohai Than at Ghugu Bari village

Overall risk score
41/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost33
Delay100
Duplication0
Agency50
Compliance0
Sanctioned
₹6.00 L
Delay
203d
Cost deviation
—
Fewer than 8 comparable works in this district and sector
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 203 days beyond expected completionPublished dates
  • Implementing agency has a 50% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.