construction of bus stand in davanagere university, tholahun

Community Buildings

Karnataka / DAVANAGERE — Davanagere(DEPUTY COMMISSIONER DAUANAGERE_IDA) · Prabha Mallikarjun (DAVANAGERE)

construction of bus stand in davanagere university, tholahunse

Overall risk score
47/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost28
Delay100
Duplication0
Agency100
Compliance0
Sanctioned
₹5.00 L
Delay
203d
Cost deviation
-35%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 203 days beyond expected completionPublished dates
  • 98% of this agency's ₹58,186,763 spend went to one vendor (NIRMITHI KENDRA DAVANGERE), across 3 vendors and 93 transactionsStatistics · Herfindahl-Hirschman index

Decision trail

Nobody has recorded a decision on this work yet.