Construction CC Road from Rajib Singha landoSubalSarkarHouse

Roads & Paving

West Bengal / MALDA — Malda(DISTRICT MAGISTRATE MALDA_IDA) · Isha Khan Choudhury (MALDAHA DAKSHIN)

Construction CC Road from Rajib Singha landoSubalSarkarHouse DEONAPUR, CHITMAHAL, bakhra bad g.p kaliachak-iii ,malda

Overall risk score
39/100
Blended from the five components below, each weighted as shown.
LOW

Risk components

Cost28
Delay100
Duplication0
Agency45
Compliance0
Sanctioned
₹3.00 L
Delay
214d
Cost deviation
-25%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 214 days beyond expected completionPublished dates
  • Implementing agency has a 45% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.