Construction of PCC Road in village kujiyamba, Block Arki
Roads & Paving
Jharkhand / KHUNTI — KHUNTI(DEPUTY COMMISSIONER KHUNTI_IDA) · Arjun Munda (KHUNTI)
Overall risk score
49/100
Blended from the five components below, each weighted as shown.
Risk components
Cost55
Delay100
Duplication0
Agency68
Compliance0
Sanctioned
₹1.50 L
Delay
806d
Cost deviation
-63%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of rangeAI · Isolation Forest (scikit-learn)
- 806 days beyond expected completionPublished dates
- 51% of this agency's ₹24,475,000 spend went to one vendor (SAHYAK ABHIYANTA SANSAD MAD), across 3 vendors and 94 transactionsStatistics · Herfindahl-Hirschman index
Decision trail
Nobody has recorded a decision on this work yet.