Construction of cement road at Jamkhed Ta.Ambad,Ta.Dist Jal

Roads & Paving

Maharashtra / JALNA — JALNA(DISTRICT COLLECTOR JALNA_IDA) · Raosaheb Dadarao Danve (JALNA)

Construction of cement road at Jamkhed Ta.Ambad,Ta.Dist Jalna

Overall risk score
54/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost64
Delay100
Duplication0
Agency87
Compliance0
Sanctioned
₹15.00 L
Delay
660d
Cost deviation
50%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹1,500,000 against a ₹1,000,000 median for Roads & Paving works in JALNA (50% above, 99 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 660 days beyond expected completionPublished dates
  • Implementing agency has a 87% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.