Kasauti can only be opened on a desktop or laptop.

Open this link on a larger screen to see the verification queue.

← Back to works

Interlocking (Foothpath) road construction Main Abadi Mahade

Roads & Paving

Rajasthan / SANCHOR — Sanchor(DISTRICT COLLECTOR Sanchor_IDA) · Lumbaram Choudhary (JALORE)

Interlocking (Foothpath) road construction Main Abadi Mahadev Mandir ke pass, G.P. Nimbau P.S. Chitalwana, Dist Jalore

Overall risk score
7/100
Blended from the five components below, each weighted as shown.
LOW

Risk components

Cost4
Delay0
Duplication0
Agency43
Compliance0
Sanctioned
₹4.99 L
Delay
0d
Cost deviation
—
Fewer than 8 comparable works in this district and sector
Work status
Completed

AI powered · gemini-flash-liteWhy was this flagged?

  • Implementing agency has a 42% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.