Construction of Lezai High School Auditorium
Education
Assam / DIBRUGARH — DIBRUGARH(DEPUTY COMMISSIONER DIBRUGARH_IDA) · Sarbananda Sonowal (DIBRUGARH)
Overall risk score
46/100
Blended from the five components below, each weighted as shown.
Risk components
Cost40
Delay100
Duplication0
Agency77
Compliance0
Sanctioned
₹10.00 L
Delay
223d
Cost deviation
0%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- 223 days beyond expected completionPublished dates
- Implementing agency has a 77% delay rate across its projectsStated compliance rule
Decision trail
Nobody has recorded a decision on this work yet.