Construction of CC road at Niwgha Bajar Tq Hadgaon Dist nand

Roads & Paving

Maharashtra / NANDED — NANDED(DISTRICT COLLECTOR NANDED_IDA) · Aashtikar Patil Nagesh Bapurao (HINGOLI)

Construction of CC road at Niwgha Bajar Tq Hadgaon Dist nanded

Overall risk score
48/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost79
Delay100
Duplication0
Agency21
Compliance0
Sanctioned
₹17.71 L
Delay
227d
Cost deviation
79%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹1,771,411 against a ₹991,540 median for Roads & Paving works in NANDED (79% above, 335 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 227 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.