Construction of a hall at Sant Sena Maharaj Temple in Ramnag

Community Buildings

Maharashtra / JALNA — JALNA(DISTRICT COLLECTOR JALNA_IDA) · Kalyan Vaijinathrao Kale (JALNA)

Construction of a hall at Sant Sena Maharaj Temple in Ramnagar, Jalna taluka.

Overall risk score
46/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost36
Delay96
Duplication0
Agency87
Compliance0
Sanctioned
₹10.00 L
Delay
173d
Cost deviation
0%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 173 days beyond expected completionPublished dates
  • Implementing agency has a 87% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.