Overall risk score
54/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency26
Compliance0
Sanctioned
₹1.50 Cr
Delay
233d
Cost deviation
788%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹15,000,000 against a ₹1,690,000 median for Roads & Paving works in CHENNAI (788% above, 35 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 233 days beyond expected completionPublished dates