Kasauti can only be opened on a desktop or laptop.

Open this link on a larger screen to see the verification queue.

← Back to works

Renovation of boundary wall, Gate, Electricity and others at

Boundary & Protection

Assam / BARPETA — BARPETA(DEPUTY COMMISSIONER BARPETA 1) · Phani Bhusan Choudhury (BARPETA)

Renovation of boundary wall, Gate, Electricity and others at Swahid Bedi at Amolapatty, Ward No 5

Overall risk score
40/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost30
Delay100
Duplication0
Agency50
Compliance0
Sanctioned
₹5.00 L
Delay
236d
Cost deviation
0%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 236 days beyond expected completionPublished dates
  • Implementing agency has a 50% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.