Renovation of boundary wall, Gate, Electricity and others at
Boundary & Protection
Assam / BARPETA — BARPETA(DEPUTY COMMISSIONER BARPETA 1) · Phani Bhusan Choudhury (BARPETA)
Renovation of boundary wall, Gate, Electricity and others at Swahid Bedi at Amolapatty, Ward No 5
Overall risk score
40/100
Blended from the five components below, each weighted as shown.
Risk components
Cost30
Delay100
Duplication0
Agency50
Compliance0
Sanctioned
₹5.00 L
Delay
236d
Cost deviation
0%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- 236 days beyond expected completionPublished dates
- Implementing agency has a 50% delay rate across its projectsStated compliance rule
Decision trail
Nobody has recorded a decision on this work yet.

