Construction of RCC Natghar at Barpara Rajahuwa Kali Mandir,

Religious & Cultural

Assam / BONGAIGAON — BONGAIGAON(Deputy Commissioner Bongaigaon_IDA) · Phani Bhusan Choudhury (BARPETA)

Construction of RCC Natghar at Barpara Rajahuwa Kali Mandir, Bongaigaon Assam (Phase-1)

Overall risk score
49/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost80
Delay100
Duplication0
Agency27
Compliance0
Sanctioned
₹18.00 L
Delay
236d
Cost deviation
80%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹1,800,000 against a ₹1,000,000 median for Religious & Cultural works in BONGAIGAON (80% above, 15 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 236 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.