Gram Lolri main antrik naali nirman

Drainage & Sanitation

Madhya Pradesh / NARSIMHAPUR — Narsimhapur(DISTRICT COLLECTOR NARSINGHPUR_IDA) · Maya Naroliya (Sitting Rajya Sabha)

Overall risk score
77/100
Blended from the five components below, each weighted as shown.
HIGH

Risk components

Cost100
Delay100
Duplication100
Agency49
Compliance0
Sanctioned
₹10.00 L
Delay
236d
Cost deviation
233%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹1,000,000 against a ₹300,000 median for Drainage & Sanitation works in NARSIMHAPUR (233% above, 18 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 236 days beyond expected completionPublished dates
  • 100% similarity with another nearby workAI · Sentence-BERT embeddings (all-MiniLM-L6-v2)
  • Implementing agency has a 49% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.

Reads as a near-duplicate of work #13043 (sentence-embedding similarity 1.00, measured by all-MiniLM-L6-v2 on meaning rather than shared words; two works can legitimately share a description, so this is a prompt to check, not a finding)