Construction of open stage and one additional room at Mejia
Education
West Bengal / BANKURA — BANKURA(DISTRICT MAGISTRATE BANKURA_IDA) · Arup Chakraborty (BANKURA)
Construction of open stage and one additional room at Mejia High School Ground under Mejia Block, Bankura District.
Overall risk score
46/100
Blended from the five components below, each weighted as shown.
Risk components
Cost70
Delay100
Duplication0
Agency25
Compliance0
Sanctioned
₹20.00 L
Delay
242d
Cost deviation
70%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹2,000,000 against a ₹1,174,098 median for Education works in BANKURA (70% above, 26 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 242 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.