Construction of Assembly Hall Ward no. 17 survey no. 532

Community Buildings

Maharashtra / DHULE — DHULE(DISTRICT COLLECTOR DHULE_IDA) · Bachhav Shobha Dinesh (DHULE)

Overall risk score
40/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost51
Delay100
Duplication0
Agency17
Compliance0
Sanctioned
₹15.00 L
Delay
241d
Cost deviation
50%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹1,500,000 against a ₹1,000,000 median for Community Buildings works in DHULE (50% above, 47 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 241 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.