Gram Panchayat Juwadi me Kholai Naale paar Stop Dam nirman
Water
Madhya Pradesh / BETUL — BETUL(DISTRICT COLLECTOR BETUL_IDA) · Durgadas D D Uikey (BETUL)
Overall risk score
63/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency89
Compliance0
Sanctioned
₹12.00 L
Delay
196d
Cost deviation
530%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹1,200,000 against a ₹190,546 median for Water works in BETUL (530% above, 74 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 196 days beyond expected completionPublished dates
- 74% of this agency's ₹56,741,127 spend went to one vendor (MP STATE AGRO INDUSTRIES DEVELOPMENT CORP LTD), across 113 vendors and 439 transactionsStatistics · Herfindahl-Hirschman index
Decision trail
Nobody has recorded a decision on this work yet.