CONSTRUCTION OF SCHOOL BUILDING OF ANJUMAN GIRL'S PRIMARY SC

Education

West Bengal / KOLKATA — KOLKATA(COMMISSIONER KOLKATA MUNICIPAL CORPORATION_IDA) · Sudip Bandyopadhyay (KOLKATA UTTAR)

CONSTRUCTION OF SCHOOL BUILDING OF ANJUMAN GIRL'S PRIMARY SCHOOL OF 35,Mofidul Islam Lane KOLKATA-700014, WARD 54,BR VI.

Overall risk score
64/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost100
Delay100
Duplication43
Agency35
Compliance0
Sanctioned
₹30.00 L
Delay
264d
Cost deviation
200%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹3,000,000 against a ₹1,000,000 median for Education works in KOLKATA (200% above, 35 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 264 days beyond expected completionPublished dates
  • 97% similarity with another nearby workAI · Sentence-BERT embeddings (all-MiniLM-L6-v2)

Decision trail

Nobody has recorded a decision on this work yet.

Reads as a near-duplicate of work #13140 (sentence-embedding similarity 0.97, measured by all-MiniLM-L6-v2 on meaning rather than shared words; two works can legitimately share a description, so this is a prompt to check, not a finding)