Construction of Community hall in front of Sheshnag temple,

Community Buildings

Rajasthan / KEKRI — Kekri(DISTRICT COLLECTOR Kekri_IDA) · Bhagirath Choudhary (AJMER)

Construction of Community hall in front of Sheshnag temple, Sevak mohalla Bhinay

Overall risk score
43/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost32
Delay100
Duplication0
Agency64
Compliance0
Sanctioned
₹5.00 L
Delay
289d
Cost deviation
0%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 289 days beyond expected completionPublished dates
  • Implementing agency has a 64% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.