Work of community hall near the place of Pu. Boghabapu in Pa
Community Buildings
Gujarat / AMRELI — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) · Bharatbhai Manubhai Sutariya (AMRELI)
Work of community hall near the place of Pu. Boghabapu in Patla village
Overall risk score
52/100
Blended from the five components below, each weighted as shown.
Risk components
Cost99
Delay100
Duplication0
Agency14
Compliance0
Sanctioned
₹9.93 L
Delay
294d
Cost deviation
99%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹993,012 against a ₹500,000 median for Community Buildings works in AMRELI (99% above, 55 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 294 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.