Construction of Congregation hall (Boikhunthadham) for Morig

Community Buildings

Assam / MARIGAON — MARIGAON(District Development Commissioner Morigaon) · Pradyut Bordoloi (NOWGONG)

Construction of Congregation hall (Boikhunthadham) for Morigaon Zilla Kendriya Bhagawat Charcha Committee, Bakorigaon.

Overall risk score
51/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost67
Delay100
Duplication0
Agency60
Compliance0
Sanctioned
₹5.00 L
Delay
296d
Cost deviation
67%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹500,000 against a ₹300,000 median for Community Buildings works in MARIGAON (67% above, 55 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 296 days beyond expected completionPublished dates
  • Implementing agency has a 60% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.