checkdam at relniya khota
Water
Rajasthan / DUNGARPUR — DUNGARPUR(DISTRICT COLLECTOR DUNGARPUR_IDA) · Manna Lal Rawat (UDAIPUR)
Overall risk score
55/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency34
Compliance0
Sanctioned
₹14.98 L
Delay
323d
Cost deviation
233%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹1,498,000 against a ₹450,000 median for Water works in DUNGARPUR (233% above, 47 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 323 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.