Installation of lift in New Chamber Building (Lala Lajpat Ra
Other
Haryana / HISAR — HISAR(DEPUTY COMMISSIONER HISSAR_IDA) · Brijendra Singh (HISAR)
Installation of lift in New Chamber Building (Lala Lajpat Rai Complex)
Overall risk score
56/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency37
Compliance0
Sanctioned
₹20.00 L
Delay
741d
Cost deviation
925%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹2,000,000 against a ₹195,187 median for Other works in HISAR (925% above, 44 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 741 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.