← Back to works

gram panchayat gudra me 150 metre c.c.road nirman karya

Roads & Paving

Chhattisgarh / SUKMA — SUKMA(Collector Sukma_IDA) · Mahesh Kashyap (BASTAR)

Overall risk score
42/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost35
Delay100
Duplication0
Agency55
Compliance0
Sanctioned
₹5.00 L
Delay
342d
Cost deviation
-16%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 342 days beyond expected completionPublished dates
  • Implementing agency has a 55% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.