Naya Tola Gauraiya Sthan under Patna Sahib Legislative Assem

Water

Bihar / PATNA — PATNA(DISTRICT PLANNING OFFICER PATNA_IDA) · Ravi Shankar Prasad (PATNA SAHIB)

Naya Tola Gauraiya Sthan under Patna Sahib Legislative Assembly with submersible and water tank stage near Jamunapur

Overall risk score
50/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost100
Delay100
Duplication0
Agency3
Compliance0
Sanctioned
₹2.33 L
Delay
744d
Cost deviation
185%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹233,000 against a ₹81,741 median for Water works in PATNA (185% above, 476 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 744 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.