Construction of Stepped Ghat in Brahamani River behind Kathi
Religious & Cultural
Jharkhand / DUMKA — DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) · Nalin Soren (DUMKA)
Construction of Stepped Ghat in Brahamani River behind Kathikund Thana, Panchayat- Telia Chak Bazar
Overall risk score
57/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency48
Compliance0
Sanctioned
₹6.00 L
Delay
362d
Cost deviation
100%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹600,000 against a ₹300,000 median for Religious & Cultural works in DUMKA (100% above, 11 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 362 days beyond expected completionPublished dates
- Implementing agency has a 48% delay rate across its projectsStated compliance rule
Decision trail
Nobody has recorded a decision on this work yet.