Concreting of road from Ambolil Junction to Polinjambalam Ju

Roads & Paving

Kerala / KOLLAM — KOLLAM(DISTRICT COLLECTOR KOLLAM_IDA) · N K Premachandran (KOLLAM)

Concreting of road from Ambolil Junction to Polinjambalam Junction in Mukundapuram, ward in Chavara Grama Panchayat

Overall risk score
54/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost100
Delay100
Duplication5
Agency19
Compliance0
Sanctioned
₹13.50 L
Delay
375d
Cost deviation
125%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹1,350,000 against a ₹600,000 median for Roads & Paving works in KOLLAM (125% above, 197 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 375 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.

Reads as a near-duplicate of work #96223 (sentence-embedding similarity 0.94, measured by all-MiniLM-L6-v2 on meaning rather than shared words; two works can legitimately share a description, so this is a prompt to check, not a finding)