Construction of Parking Plaza at Badlapur Railway Station.
Other
Maharashtra / THANE — THANE(DISTRICT COLLECTOR THANE_IDA) · Kapil Moreshwar Patil (BHIWANDI)
Overall risk score
55/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency33
Compliance0
Sanctioned
₹50.00 L
Delay
544d
Cost deviation
278%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹5,000,000 against a ₹1,323,585 median for Other works in THANE (278% above, 20 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 544 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.