Construction of Bridge across the Vallakodu Drain in MMPuram
Roads & Paving
Andhra Pradesh / ELURU — Eluru(DISTRICT COLLECTOR ELURU_IDA) · Kotagiri Sridhar (ELURU)
Construction of Bridge across the Vallakodu Drain in MMPuram H/o Pulla
Overall risk score
54/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency26
Compliance0
Sanctioned
₹25.00 L
Delay
545d
Cost deviation
150%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹2,500,000 against a ₹1,000,000 median for Roads & Paving works in ELURU (150% above, 25 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 545 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.