Construction and Earth filling of road from Pathisseriy - P

Roads & Paving

Kerala / ALAPPUZHA — ALAPPUZHA(DISTRICT COLLECTOR ALAPPUZHA_IDA) · Kodikunnil Suresh (MAVELIKKARA)

Construction and Earth filling of road from Pathisseriy - Paloothara in ward 7, Chunakkara Grama Panchayath

Overall risk score
54/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost100
Delay100
Duplication0
Agency28
Compliance0
Sanctioned
₹25.00 L
Delay
545d
Cost deviation
157%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹2,500,000 against a ₹972,457 median for Roads & Paving works in ALAPPUZHA (157% above, 132 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 545 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.