SARVJANIK SABHA BHAWAN NIRMAN KARYA ,ROHAT
Community Buildings
Rajasthan / PALI — PALI(DISTRICT COLLECTOR PALI_IDA) · P P Chaudhary (PALI)
Overall risk score
55/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency31
Compliance0
Sanctioned
₹10.00 L
Delay
751d
Cost deviation
100%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹1,000,000 against a ₹500,000 median for Community Buildings works in PALI (100% above, 166 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 751 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.