← Back to works

Construction of new floor of the existing building of Netaji

Education

Andhra Pradesh / VISAKHAPATNAM — Visakhapatnam(DISTRICT COLLECTOR VISAKHAPATNAM_IDA) · S Niranjan Reddy (Sitting Rajya Sabha)

Construction of new floor of the existing building of Netaji Subhash Chandra Bose Awasiya Vidyalayam, Bheemunipatnam.

Overall risk score
70/100
Blended from the five components below, each weighted as shown.
HIGH

Risk components

Cost100
Delay85
Duplication100
Agency26
Compliance0
Sanctioned
₹80.00 L
Delay
153d
Cost deviation
371%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹8,000,000 against a ₹1,700,000 median for Education works in VISAKHAPATNAM (371% above, 32 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 153 days beyond expected completionPublished dates
  • 100% similarity with another nearby workAI · Sentence-BERT embeddings (all-MiniLM-L6-v2)

Decision trail

Nobody has recorded a decision on this work yet.

Reads as a near-duplicate of work #51286 (sentence-embedding similarity 1.00, measured by all-MiniLM-L6-v2 on meaning rather than shared words; two works can legitimately share a description, so this is a prompt to check, not a finding)