MP/2324/3146 Construction of community Hall in front of Bank
Community Buildings
Maharashtra / NASHIK — NASHIK(DISTRICT COLLECTOR NASHIK_IDA) · Hemant Tukaram Godse (NASHIK)
MP/2324/3146 Construction of community Hall in front of Bankatswamy Mangal Office at Waghere Dist.Igatpuri Dist.Nashik.(Group No.V Sub Division-1)
Overall risk score
42/100
Blended from the five components below, each weighted as shown.
Risk components
Cost59
Delay100
Duplication0
Agency16
Compliance0
Sanctioned
₹14.91 L
Delay
561d
Cost deviation
51%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹1,491,000 against a ₹990,530 median for Community Buildings works in NASHIK (51% above, 162 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 561 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.