Construction of community centre near Vishwakarma temple in
Community Buildings
Jharkhand / HAZARIBAGH — HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) · Jayant Sinha (HAZARIBAGH)
Construction of community centre near Vishwakarma temple in Panchayat Pandeybara, village Arapagar.
Overall risk score
65/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency100
Compliance0
Sanctioned
₹10.00 L
Delay
569d
Cost deviation
100%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹1,000,000 against a ₹500,000 median for Community Buildings works in HAZARIBAGH (100% above, 50 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 569 days beyond expected completionPublished dates
- 100% of this agency's ₹39,899,950 spend went to one vendor (RAJ KUMAR SAGAR), across 1 vendor and 97 transactionsStatistics · Herfindahl-Hirschman index
Decision trail
Nobody has recorded a decision on this work yet.