gram meharu me prahalad gurjar ke makan se ramasvarup saahu

Roads & Paving

Rajasthan / KEKRI — Kekri(DISTRICT COLLECTOR Kekri_IDA) · Sukhbir Singh Jaunapuria (TONK-SAWAI MADHOPUR)

gram meharu me prahalad gurjar ke makan se ramasvarup saahu ke makaan ki or CC road nirmaan kaary may nali

Overall risk score
42/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost32
Delay100
Duplication0
Agency64
Compliance0
Sanctioned
₹5.00 L
Delay
570d
Cost deviation
0%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 570 days beyond expected completionPublished dates
  • Implementing agency has a 64% delay rate across its projectsStated compliance rule

Decision trail