Construction of Marwadi Samaj Community Center

Community Buildings

Odisha / KALAHANDI — KALAHANDI(DISTRICT COLLECTOR KALAHANDI_IDA) · Basanta Kumar Panda (KALAHANDI)

Overall risk score
55/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost100
Delay100
Duplication0
Agency31
Compliance0
Sanctioned
₹5.00 L
Delay
574d
Cost deviation
100%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹500,000 against a ₹250,000 median for Community Buildings works in KALAHANDI (100% above, 114 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 574 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.