Construction of hall at Ravidasia Dharmashala.

Community Buildings

Karnataka / KAITHAL — KAITHAL(DC CUM NODAL OFFICERS MPLADS) · Syed Naseer Hussain (Sitting Rajya Sabha)

Overall risk score
60/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost36
Delay100
Duplication100
Agency43
Compliance0
Sanctioned
₹6.00 L
Delay
257d
Cost deviation
20%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 257 days beyond expected completionPublished dates
  • 100% similarity with another nearby workAI · Sentence-BERT embeddings (all-MiniLM-L6-v2)
  • Implementing agency has a 43% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.

Reads as a near-duplicate of work #52301 (sentence-embedding similarity 1.00, measured by all-MiniLM-L6-v2 on meaning rather than shared words; two works can legitimately share a description, so this is a prompt to check, not a finding)