Construction of Post mortum Room at CHC Bhitarwar Recomme
Health
Madhya Pradesh / GWALIOR — GWALIOR(DISTRICT COLLECTOR GWALIOR_IDA) · Vivek Narayan Shejwalkar (GWALIOR)
Construction of Post mortum Room at CHC Bhitarwar Recommended Amount As per TS
Overall risk score
54/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency29
Compliance0
Sanctioned
₹20.09 L
Delay
757d
Cost deviation
144%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹2,009,000 against a ₹825,000 median for Health works in GWALIOR (144% above, 10 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 757 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.