Construction of Jijamata Girls High School balance work at M
Roads & Paving
Karnataka / BIDAR — BIDAR(DEPUTY COMMISSIONER BIDAR_IDA) · Bhagwanth Khuba (BIDAR)
Construction of Jijamata Girls High School balance work at Mailoor Road Bidar
Overall risk score
53/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency18
Compliance0
Sanctioned
₹9.00 L
Delay
581d
Cost deviation
101%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹900,000 against a ₹447,238 median for Roads & Paving works in BIDAR (101% above, 38 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 581 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.