Construction of Community infrastructure & public utility bu- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 614 days beyond expected completion
| SRI SATHYA SAI | ₹24.50 L | MEDIUM 51 |
Construction of Community Hall at Kaganapalli Village of Gor- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 614 days beyond expected completion
| SRI SATHYA SAI | ₹10.00 L | MEDIUM 47 |
Providing Encasing of R.C.C Pipes with Concrete for cause wa- ₹3,783,871 against a ₹499,555 median for Roads & Paving works in SRI SATHYA SAI (657% above, 102 peer works)
- 63% of this agency's ₹66,872,918 spend went to one vendor (K RAMESH BABU), across 17 vendors and 82 transactions
| SRI SATHYA SAI | ₹37.84 L | LOW 34 |
Construction of C.C road for cause way across penna river on- ₹3,812,295 against a ₹499,555 median for Roads & Paving works in SRI SATHYA SAI (663% above, 102 peer works)
- 63% of this agency's ₹66,872,918 spend went to one vendor (K RAMESH BABU), across 17 vendors and 82 transactions
| SRI SATHYA SAI | ₹38.12 L | LOW 34 |
Construction of 6 Mts span RCC slab culvert with 2 vents acr- ₹3,779,982 against a ₹499,555 median for Roads & Paving works in SRI SATHYA SAI (657% above, 102 peer works)
- 63% of this agency's ₹66,872,918 spend went to one vendor (K RAMESH BABU), across 17 vendors and 82 transactions
| SRI SATHYA SAI | ₹37.80 L | LOW 34 |
Construction of Culvert in KM 0/5 to 2/0 on the road from NH- ₹3,213,626 against a ₹499,555 median for Roads & Paving works in SRI SATHYA SAI (543% above, 102 peer works)
- 63% of this agency's ₹66,872,918 spend went to one vendor (K RAMESH BABU), across 17 vendors and 82 transactions
| SRI SATHYA SAI | ₹32.14 L | LOW 34 |
Construction of Community infrastructure & public utility bu- ₹2,419,187 against a ₹1,000,000 median for Community Buildings works in SRI SATHYA SAI (142% above, 44 peer works)
- 63% of this agency's ₹66,872,918 spend went to one vendor (K RAMESH BABU), across 17 vendors and 82 transactions
| SRI SATHYA SAI | ₹24.19 L | LOW 34 |
Construction of Approach road from R & B Road to Madhurepall- ₹1,630,319 against a ₹499,555 median for Roads & Paving works in SRI SATHYA SAI (226% above, 102 peer works)
- 63% of this agency's ₹66,872,918 spend went to one vendor (K RAMESH BABU), across 17 vendors and 82 transactions
| SRI SATHYA SAI | ₹16.30 L | LOW 34 |
Construction of Causeway (Road Dam) across Penna River on th- ₹2,161,321 against a ₹499,555 median for Roads & Paving works in SRI SATHYA SAI (333% above, 102 peer works)
- 63% of this agency's ₹66,872,918 spend went to one vendor (K RAMESH BABU), across 17 vendors and 82 transactions
| SRI SATHYA SAI | ₹21.61 L | LOW 34 |
Providing protection work to causeway across Penna River on - ₹2,000,000 against a ₹499,555 median for Roads & Paving works in SRI SATHYA SAI (300% above, 102 peer works)
- 63% of this agency's ₹66,872,918 spend went to one vendor (K RAMESH BABU), across 17 vendors and 82 transactions
| SRI SATHYA SAI | ₹20.00 L | LOW 34 |