264 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | HARIDWAR(DISTRICT MAGISTRATE HARIDWAR_IDA) 3 high risk | 264 | 81 | ₹23.45 Cr | 100 | 34.8 | Manju Choudhary 22% of spend · 41 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Kalpana Saini Sitting Rajya Sabha | 128 | ₹11.43 Cr | 46 |
| Naresh Bansal Sitting Rajya Sabha | 112 | ₹9.48 Cr | 51 |
| Trivendra Singh Rawat HARDWAR | 21 | ₹2.33 Cr | 2 |
| Mahendra Bhatt Sitting Rajya Sabha | 3 | ₹20.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 144 | ₹11.35 Cr | 67 |
| Religious & Cultural | 38 | ₹3.93 Cr | 8 |
| Drainage & Sanitation | 17 | ₹1.68 Cr | 5 |
| Education | 16 | ₹1.49 Cr | 2 |
| Community Buildings | 12 | ₹1.39 Cr | 6 |
| Equipment & Vehicles | 11 | ₹1.78 Cr | 1 |
| Street Lighting | 9 | ₹80.49 L | 5 |
| Water | 6 | ₹26.98 L | 2 |
| Other | 4 | ₹13.39 L | 2 |
| Sports | 4 | ₹46.62 L | 1 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of interlocking tiles road from Sardar Mahavir ₹1,500,000 against a ₹500,000 median for Roads & Paving works in HARIDWAR (200% above, 392 peer works) | HARIDWAR(DISTRICT MAGISTRATE HARIDWAR_IDA) | Recommended | ₹15.00 L | 213 d | +200% | 73.5 | HIGH |
| janpad haridwar ke gaindikhata me shrikrishanyan gaurakshash ₹1,000,000 against a ₹200,000 median for Water works in HARIDWAR (400% above, 12 peer works) | HARIDWAR(DISTRICT MAGISTRATE HARIDWAR_IDA) | Recommended | ₹10.00 L | 169 d | +400% | 71.9 | HIGH |
| For installing Solar Plant in Prachin Avdhoot Ashram, Post G ₹2,500,000 against a ₹1,000,000 median for Religious & Cultural works in HARIDWAR (150% above, 77 peer works) | HARIDWAR(DISTRICT MAGISTRATE HARIDWAR_IDA) | Recommended | ₹25.00 L | 169 d | +150% | 71.9 | HIGH |
| GRAM SIKRAUDHA MEIN 11 KV LINE KO STHANTARAN KA KARYA..
IA( ₹261,841 against a ₹144,284 median for Other works in HARIDWAR (81% above, 8 peer works) | HARIDWAR(DISTRICT MAGISTRATE HARIDWAR_IDA) | Recommended | ₹2.62 L | 555 d | +81% | 68.8 | MEDIUM |
| gram amarpur quazi mein main road se dharamveer ke makan ki ₹996,000 against a ₹500,000 median for Roads & Paving works in HARIDWAR (99% above, 392 peer works) | HARIDWAR(DISTRICT MAGISTRATE HARIDWAR_IDA) | Recommended | ₹9.96 L | 99 d | +99% | 62.0 | MEDIUM |
| KOTWALI MANGLAUR MEIN MAHILA HELP DESK HETU EK ROOM EVAM TOI Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | HARIDWAR(DISTRICT MAGISTRATE HARIDWAR_IDA) | Recommended | ₹10.00 L | 578 d | +1% | 61.0 | MEDIUM |
| THANA PATHRI MEIN MAHILA HELP DESK HETU EK ROOM EVAM TOILET Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | HARIDWAR(DISTRICT MAGISTRATE HARIDWAR_IDA) | Recommended | ₹10.00 L | 578 d | +1% | 61.0 | MEDIUM |
| THANA PIRAN KALIYAR MEIN MAHILA HELP DESK HETU EK ROOM EVAM Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | HARIDWAR(DISTRICT MAGISTRATE HARIDWAR_IDA) | Recommended | ₹10.00 L | 578 d | +1% | 61.0 | MEDIUM |
| THANA BHAGWANPUR MEIN MAHILA HELP DESK HETU EK ROOM EVAM TOI Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | HARIDWAR(DISTRICT MAGISTRATE HARIDWAR_IDA) | Recommended | ₹10.00 L | 578 d | +1% | 61.0 | MEDIUM |
| Setting up a Solar Power Plant in Press Club Haridwar ₹1,000,000 against a ₹670,000 median for Street Lighting works in HARIDWAR (49% above, 17 peer works) | HARIDWAR(DISTRICT MAGISTRATE HARIDWAR_IDA) | Recommended | ₹10.00 L | 196 d | +49% | 60.8 | MEDIUM |
| Construction of C.C. road from the house of Mr. Mamchand to ₹1,200,000 against a ₹500,000 median for Roads & Paving works in HARIDWAR (140% above, 392 peer works) | HARIDWAR(DISTRICT MAGISTRATE HARIDWAR_IDA) | Recommended | ₹12.00 L | 85 d | +140% | 60.3 | MEDIUM |
| Construction of class room in Harishchander Kailashwati Sara ₹1,500,000 against a ₹1,000,000 median for Religious & Cultural works in HARIDWAR (50% above, 77 peer works) | HARIDWAR(DISTRICT MAGISTRATE HARIDWAR_IDA) | Recommended | ₹15.00 L | 169 d | +50% | 59.4 | MEDIUM |
| Construction of roof at cremation ground in Scheduled Caste 196 days beyond expected completion | HARIDWAR(DISTRICT MAGISTRATE HARIDWAR_IDA) | Recommended | ₹10.00 L | 196 d | 0% | 58.0 | MEDIUM |
| To purchase a hearse for Nirvana Ashram, Malviya Chowk, Gane Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | HARIDWAR(DISTRICT MAGISTRATE HARIDWAR_IDA) | Recommended | ₹25.65 L | 142 d | +23% | 57.8 | MEDIUM |
| Construction of roof at the cremation ground of Scheduled Ca 175 days beyond expected completion | HARIDWAR(DISTRICT MAGISTRATE HARIDWAR_IDA) | Recommended | ₹10.00 L | 175 d | 0% | 56.9 | MEDIUM |