Open this link on a larger screen to see the verification queue.
37 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Amethi(DISTRICT MAGISTRAE AMETHI_IDA) 1 high risk | 37 | 18 | ₹7.53 Cr | 12 | 35.9 | AADI AND RUDRANSH CONSTRUCTION COMPANY 72% of spend · 11 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Kishori Lal AMETHI | 30 | ₹6.92 Cr | 8 |
| Sanjay Seth Sitting Rajya Sabha | 3 | ₹18.03 L | 2 |
| Seema Dwivedi Sitting Rajya Sabha | 2 | ₹12.99 L | 1 |
| Laxmi Kant Bajpai Sitting Rajya Sabha | 2 | ₹30.03 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Street Lighting | 20 | ₹5.74 Cr | 7 |
| Equipment & Vehicles | 4 | ₹39.97 L | 0 |
| Education | 4 | ₹48.26 L | 3 |
| Roads & Paving | 3 | ₹36.95 L | 1 |
| Other | 2 | ₹8.03 L | 1 |
| Water | 1 | ₹5.31 L | 0 |
| Community Buildings | 1 | ₹24.50 L | 0 |
| Health | 1 | ₹12.00 L | 0 |
| Boundary & Protection | 1 | ₹4.50 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Block Gauriganj me Tribhuwan nath Siksha Nikaten Pure Keshar ₹1,200,000 against a ₹625,000 median for Education works in AMETHI (92% above, 8 peer works) | Amethi(DISTRICT MAGISTRAE AMETHI_IDA) | Recommended | ₹12.00 L | 752 d | +92% | 81.0 | HIGH |
| Installation of 50 solar street lights in 2 blocks i.e., san 143 days beyond expected completion | Amethi(DISTRICT MAGISTRAE AMETHI_IDA) | Recommended | ₹10.00 L | 143 d | 0% | 61.4 | MEDIUM |
| Installation of 241 (Two Hundred Forty One) solar street lig ₹5,413,824 against a ₹1,000,000 median for Street Lighting works in AMETHI (441% above, 24 peer works) | Amethi(DISTRICT MAGISTRAE AMETHI_IDA) | Recommended | ₹54.14 L | 156 d | +441% | 61.1 | MEDIUM |
| Installation of 143(One Hundred Forty Three) solar street li ₹3,212,352 against a ₹1,000,000 median for Street Lighting works in AMETHI (221% above, 24 peer works) | Amethi(DISTRICT MAGISTRAE AMETHI_IDA) | Recommended | ₹32.12 L | 156 d | +221% | 61.1 | MEDIUM |
| Installation of 287 (Two Hundred Eighty Seven) solar street ₹6,447,168 against a ₹1,000,000 median for Street Lighting works in AMETHI (545% above, 24 peer works) | Amethi(DISTRICT MAGISTRAE AMETHI_IDA) | Recommended | ₹64.47 L | 156 d | +545% | 59.7 | MEDIUM |
| For shifting of 11k electric high tension line in Amethi bl 143 days beyond expected completion | Amethi(DISTRICT MAGISTRAE AMETHI_IDA) | Recommended | ₹3.20 L | 143 d | 0% | 58.7 | MEDIUM |
| Construction of 300 Meter CC Road and Drainage ₹2,472,000 against a ₹1,276,288 median for Roads & Paving works in AMETHI (94% above, 64 peer works) | Amethi(DISTRICT MAGISTRAE AMETHI_IDA) | Recommended | ₹24.72 L | — | +94% | 56.4 | MEDIUM |
| Installation of 117 (one hundred seventeen) solar street lig ₹2,628,288 against a ₹1,000,000 median for Street Lighting works in AMETHI (163% above, 24 peer works) | Amethi(DISTRICT MAGISTRAE AMETHI_IDA) | Recommended | ₹26.28 L | 110 d | +163% | 53.3 | MEDIUM |
| Installation of 137 (one hundred thirty-seven) solar street ₹3,077,568 against a ₹1,000,000 median for Street Lighting works in AMETHI (208% above, 24 peer works) | Amethi(DISTRICT MAGISTRAE AMETHI_IDA) | Recommended | ₹30.78 L | 110 d | +208% | 53.3 | MEDIUM |
| Release a total amount of Rs. 6,25,000(Six Lakh Twenty Five 338 days beyond expected completion | Amethi(DISTRICT MAGISTRAE AMETHI_IDA) | Recommended | ₹6.25 L | 338 d | 0% | 47.8 | MEDIUM |
| Release a total amount of Rs. 6,25,000 (Six Lakh Twenty Five 338 days beyond expected completion | Amethi(DISTRICT MAGISTRAE AMETHI_IDA) | Recommended | ₹6.25 L | 338 d | 0% | 47.8 | MEDIUM |
| Installation of 36 (Thirty Six) high mast electric lights as ₹7,200,000 against a ₹1,000,000 median for Street Lighting works in AMETHI (620% above, 24 peer works) | Amethi(DISTRICT MAGISTRAE AMETHI_IDA) | Recommended | ₹72.00 L | 18 d | +620% | 40.5 | MEDIUM |
| Installation of 100 (One Hundred) solar street lights across ₹2,149,700 against a ₹1,000,000 median for Street Lighting works in AMETHI (115% above, 24 peer works) | Amethi(DISTRICT MAGISTRAE AMETHI_IDA) | Recommended | ₹21.50 L | — | +115% | 38.0 | LOW |
| Installation of 250 (Two Hundred Fifty) solar street lights ₹5,374,250 against a ₹1,000,000 median for Street Lighting works in AMETHI (437% above, 24 peer works) | Amethi(DISTRICT MAGISTRAE AMETHI_IDA) | Recommended | ₹53.74 L | — | +437% | 38.0 | LOW |
| For the purchase of a 32-seater bus for Sainik School, Kauha ₹2,376,000 against a ₹625,000 median for Education works in AMETHI (280% above, 8 peer works) | Amethi(DISTRICT MAGISTRAE AMETHI_IDA) | Completed | ₹23.76 L | — | +280% | 38.0 | LOW |