165 works across 1 implementing agency, recommended by 4 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | TIRUNELVELI(DISTRICT COLLECTOR TIRUNELVELI_IDA) | 165 | 61 | ₹14.92 Cr | 3 | 14.9 | SAI IT SYSTEMS 16% of spend · 27 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Robert Bruce C TIRUNELVELI | 134 | ₹12.01 Cr | 2 |
| I.S. Inbadurai Sitting Rajya Sabha | 24 | ₹1.42 Cr | 0 |
| P. Wilson Sitting Rajya Sabha | 5 | ₹1.00 Cr | 1 |
| R. Dharmar Sitting Rajya Sabha | 2 | ₹49.85 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Education | 50 | ₹2.73 Cr | 1 |
| Roads & Paving | 29 | ₹3.28 Cr | 0 |
| Community Buildings | 24 | ₹2.75 Cr | 1 |
| Street Lighting | 22 | ₹1.64 Cr | 0 |
| Water | 11 | ₹85.30 L | 1 |
| Boundary & Protection | 9 | ₹1.57 Cr | 0 |
| Drainage & Sanitation | 8 | ₹1.03 Cr | 0 |
| Religious & Cultural | 5 | ₹42.69 L | 0 |
| Equipment & Vehicles | 4 | ₹33.40 L | 0 |
| Other | 2 | ₹28.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of a kitchen, toilet and borewell at the Rottut ₹1,500,000 against a ₹428,879 median for Water works in TIRUNELVELI (250% above, 17 peer works) | TIRUNELVELI(DISTRICT COLLECTOR TIRUNELVELI_IDA) | Recommended | ₹15.00 L | 183 d | +250% | 51.4 | MEDIUM |
| Construction of Community Hall at Ananthakrishnapuram Ward N ₹3,000,000 against a ₹912,508 median for Community Buildings works in TIRUNELVELI (229% above, 71 peer works) | TIRUNELVELI(DISTRICT COLLECTOR TIRUNELVELI_IDA) | Recommended | ₹30.00 L | 190 d | +229% | 51.4 | MEDIUM |
| Construction of a dining hall at St Josephs Higher Secondary ₹1,840,000 against a ₹298,900 median for Education works in TIRUNELVELI (516% above, 65 peer works) | TIRUNELVELI(DISTRICT COLLECTOR TIRUNELVELI_IDA) | Recommended | ₹18.40 L | — | +516% | 46.4 | MEDIUM |
| construction of flood control Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | TIRUNELVELI(DISTRICT COLLECTOR TIRUNELVELI_IDA) | Completed | ₹24.96 L | — | +11% | 38.0 | LOW |
| Construction of flood Production wall in Aaladiyur Village Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | TIRUNELVELI(DISTRICT COLLECTOR TIRUNELVELI_IDA) | Completed | ₹24.90 L | — | +11% | 37.9 | LOW |
| Construction of new PDS shop building opposite Tirunelveli T ₹1,300,000 against a ₹912,508 median for Community Buildings works in TIRUNELVELI (42% above, 71 peer works) | TIRUNELVELI(DISTRICT COLLECTOR TIRUNELVELI_IDA) | Recommended | ₹13.00 L | 183 d | +42% | 37.4 | LOW |
| Construction Of New PDS shop at C.N Village ward no.29 in Ti Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | TIRUNELVELI(DISTRICT COLLECTOR TIRUNELVELI_IDA) | Recommended | ₹13.00 L | 183 d | 0% | 37.4 | LOW |
| Providing 12 Meter High-mast Light pole with 200W LED Dimmab 190 days beyond expected completion | TIRUNELVELI(DISTRICT COLLECTOR TIRUNELVELI_IDA) | Recommended | ₹7.75 L | 190 d | +3% | 35.1 | LOW |
| Providing 12 Meter High-mast Light pole with 200W LED Dimmab 190 days beyond expected completion | TIRUNELVELI(DISTRICT COLLECTOR TIRUNELVELI_IDA) | Recommended | ₹7.75 L | 190 d | +3% | 35.1 | LOW |
| Construction of drainage in Ward No. 1 Kamaraj Street, Chera 183 days beyond expected completion | TIRUNELVELI(DISTRICT COLLECTOR TIRUNELVELI_IDA) | Recommended | ₹5.00 L | 183 d | -75% | 33.0 | LOW |
| Construction of a deep well and installation of a Syntex tan 131 days beyond expected completion | TIRUNELVELI(DISTRICT COLLECTOR TIRUNELVELI_IDA) | Recommended | ₹2.70 L | 131 d | -37% | 32.9 | LOW |
| Construction of a deep well and installation of a Syntex tan 131 days beyond expected completion | TIRUNELVELI(DISTRICT COLLECTOR TIRUNELVELI_IDA) | Recommended | ₹2.70 L | 131 d | -37% | 32.9 | LOW |
| Construction of Anganwadi Building at Palayamchettikulam Pan ₹1,600,000 against a ₹298,900 median for Education works in TIRUNELVELI (435% above, 65 peer works) | TIRUNELVELI(DISTRICT COLLECTOR TIRUNELVELI_IDA) | Recommended | ₹16.00 L | 42 d | +435% | 32.2 | LOW |
| Construction of Community Building at Itteri Panchayat in Pa ₹3,000,000 against a ₹912,508 median for Community Buildings works in TIRUNELVELI (229% above, 71 peer works) | TIRUNELVELI(DISTRICT COLLECTOR TIRUNELVELI_IDA) | Recommended | ₹30.00 L | 36 d | +229% | 31.4 | LOW |
| construction of toilets for male Students at Sacred Heart Hi 100% similarity with another nearby work | TIRUNELVELI(DISTRICT COLLECTOR TIRUNELVELI_IDA) | Recommended | ₹20.80 L | — | +3% | 30.6 | LOW |