121 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Ranipet(District Collector, Ranipet_2) | 121 | 24 | ₹10.85 Cr | 7 | 18.4 | AVN CONSTRUCTIONS 9% of spend · 31 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Dr. S Jagathratchakan ARAKKONAM | 119 | ₹10.70 Cr | 7 |
| M. Dhanapal Sitting Rajya Sabha | 2 | ₹15.00 L | 0 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Education | 36 | ₹2.36 Cr | 1 |
| Roads & Paving | 29 | ₹3.09 Cr | 2 |
| Community Buildings | 16 | ₹1.82 Cr | 1 |
| Water | 9 | ₹54.33 L | 3 |
| Equipment & Vehicles | 9 | ₹82.95 L | 0 |
| Other | 6 | ₹93.00 L | 0 |
| Street Lighting | 6 | ₹43.00 L | 0 |
| Drainage & Sanitation | 5 | ₹27.50 L | 0 |
| Religious & Cultural | 4 | ₹37.00 L | 0 |
| Sports | 1 | ₹20.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Cement Road 266 days beyond expected completion | Ranipet(District Collector, Ranipet_2) | Recommended | ₹5.00 L | 266 d | -44% | 55.4 | MEDIUM |
| Installation of Borewell 227 days beyond expected completion | Ranipet(District Collector, Ranipet_2) | Recommended | ₹2.10 L | 227 d | -35% | 54.5 | MEDIUM |
| Installation of Borewell 227 days beyond expected completion | Ranipet(District Collector, Ranipet_2) | Recommended | ₹2.10 L | 227 d | -35% | 54.5 | MEDIUM |
| Installation of Borewell 227 days beyond expected completion | Ranipet(District Collector, Ranipet_2) | Recommended | ₹2.10 L | 227 d | -35% | 54.5 | MEDIUM |
| Construction of Bus stand Entrance Arch ₹2,000,000 against a ₹968,340 median for Community Buildings works in RANIPET (107% above, 20 peer works) | Ranipet(District Collector, Ranipet_2) | Recommended | ₹20.00 L | 209 d | +107% | 52.4 | MEDIUM |
| Construction of Anganwadi Building in ward 2 Walajah nagaram ₹1,800,000 against a ₹500,000 median for Education works in RANIPET (260% above, 49 peer works) | Ranipet(District Collector, Ranipet_2) | Recommended | ₹18.00 L | 163 d | +260% | 50.0 | MEDIUM |
| construction of Anganwadi building in nemili,Vanniyar road ₹1,550,000 against a ₹900,000 median for Roads & Paving works in RANIPET (72% above, 51 peer works) | Ranipet(District Collector, Ranipet_2) | Recommended | ₹15.50 L | 266 d | +72% | 45.5 | MEDIUM |
| Construction of Fair Price Shop in Arakkonam ward no 21 ₹1,400,000 against a ₹968,340 median for Community Buildings works in RANIPET (45% above, 20 peer works) | Ranipet(District Collector, Ranipet_2) | Recommended | ₹14.00 L | 266 d | +45% | 39.9 | LOW |
| Construction of fair Price Shop in Ward Numbe No 18 Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Ranipet(District Collector, Ranipet_2) | Recommended | ₹19.00 L | 163 d | 0% | 38.3 | LOW |
| construction of Bus stop Shelter in in Arakonam Ward 8 Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | Ranipet(District Collector, Ranipet_2) | Recommended | ₹8.00 L | 266 d | -17% | 37.5 | LOW |
| Supply , installation and Commissioning of Reverse Osmosis P ₹1,053,000 against a ₹325,000 median for Water works in RANIPET (224% above, 12 peer works) | Ranipet(District Collector, Ranipet_2) | Recommended | ₹10.53 L | 72 d | +224% | 37.4 | LOW |
| Construction of Multi Purpose Building at Ward no 19,First M 266 days beyond expected completion | Ranipet(District Collector, Ranipet_2) | Recommended | ₹7.00 L | 266 d | -22% | 37.0 | LOW |
| Construction o Shelter 266 days beyond expected completion | Ranipet(District Collector, Ranipet_2) | Recommended | ₹7.00 L | 266 d | -28% | 37.0 | LOW |
| Construction of Toilet Blocks in Elemntary Scool in Ayarpadi 266 days beyond expected completion | Ranipet(District Collector, Ranipet_2) | Recommended | ₹6.50 L | 266 d | 0% | 36.8 | LOW |
| Construction of Culvert at 10th ward jabar Masthan darga Roa 227 days beyond expected completion | Ranipet(District Collector, Ranipet_2) | Recommended | ₹2.00 L | 227 d | -78% | 34.6 | LOW |