29 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | NAGAPATTINAM(DISTRICT COLLECTOR NAGAPATTINAM_4) | 29 | 7 | ₹4.45 Cr | 2 | 19.9 | Aakash Construction 21% of spend · 15 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Selvaraj V NAGAPATTINAM | 28 | ₹4.26 Cr | 1 |
| S. Kalyanasundaram Sitting Rajya Sabha | 1 | ₹18.91 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 8 | ₹1.13 Cr | 1 |
| Community Buildings | 7 | ₹1.80 Cr | 0 |
| Street Lighting | 6 | ₹45.81 L | 1 |
| Other | 3 | ₹30.00 L | 0 |
| Religious & Cultural | 2 | ₹36.00 L | 0 |
| Water | 1 | ₹10.00 L | 0 |
| Education | 1 | ₹10.00 L | 0 |
| Boundary & Protection | 1 | ₹21.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| BT of road at Panchanathikulam West Kondankadu south, north ₹2,912,000 against a ₹1,000,000 median for Roads & Paving works in NAGAPATTINAM (191% above, 11 peer works) | NAGAPATTINAM(DISTRICT COLLECTOR NAGAPATTINAM_4) | Recommended | ₹29.12 L | 196 d | +191% | 53.3 | MEDIUM |
| Nagapattinam District, Tirukuwela Panchayat Tirukuwela South ₹1,890,616 against a ₹480,000 median for Street Lighting works in NAGAPATTINAM (294% above, 19 peer works) | NAGAPATTINAM(DISTRICT COLLECTOR NAGAPATTINAM_4) | Completed | ₹18.91 L | — | +294% | 48.3 | MEDIUM |
| Installation of Hi-Mast light in Main Street in Anthakudi Pa 196 days beyond expected completion | NAGAPATTINAM(DISTRICT COLLECTOR NAGAPATTINAM_4) | Recommended | ₹4.80 L | 196 d | 0% | 35.5 | LOW |
| CONSTRUCTION OF BUS SHELTER FOR SANTHAIPETTAI AT THIRUMARUGA ₹4,000,000 against a ₹2,297,972 median for Community Buildings works in NAGAPATTINAM (74% above, 10 peer works) | NAGAPATTINAM(DISTRICT COLLECTOR NAGAPATTINAM_4) | Recommended | ₹40.00 L | 84 d | +74% | 33.5 | LOW |
| Construction of Bus Shelter at Bazaar Street Thevur Village ₹4,000,000 against a ₹2,297,972 median for Community Buildings works in NAGAPATTINAM (74% above, 10 peer works) | NAGAPATTINAM(DISTRICT COLLECTOR NAGAPATTINAM_4) | Recommended | ₹40.00 L | 84 d | +74% | 33.5 | LOW |
| CONSTRUCTION OF BUS PASSENGER SHELTER AT THOPPUTHURAI OF VED ₹4,000,000 against a ₹2,297,972 median for Community Buildings works in NAGAPATTINAM (74% above, 10 peer works) | NAGAPATTINAM(DISTRICT COLLECTOR NAGAPATTINAM_4) | Recommended | ₹40.00 L | 84 d | +74% | 33.5 | LOW |
| CONSTRUCTION OF FIRST FLOOR BUILDING TO COMMUNITY HALL TSUNA Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range | NAGAPATTINAM(DISTRICT COLLECTOR NAGAPATTINAM_4) | Recommended | ₹30.00 L | 84 d | +31% | 30.9 | LOW |
| Erection of High-Mass Light at Keelavenmani of Venmani Panch ₹770,000 against a ₹480,000 median for Street Lighting works in NAGAPATTINAM (60% above, 19 peer works) | NAGAPATTINAM(DISTRICT COLLECTOR NAGAPATTINAM_4) | Recommended | ₹7.70 L | 84 d | +60% | 30.1 | LOW |
| PROVIDING OF BT ROAD AT PANCHANATHIKULAM WEST KONDANKADU SOU ₹2,910,947 against a ₹1,000,000 median for Roads & Paving works in NAGAPATTINAM (191% above, 11 peer works) | NAGAPATTINAM(DISTRICT COLLECTOR NAGAPATTINAM_4) | Completed | ₹29.11 L | — | +191% | 28.3 | LOW |
| Providing the New Shuttering arrangements to the Vent No.03 100% similarity with another nearby work | NAGAPATTINAM(DISTRICT COLLECTOR NAGAPATTINAM_4) | Recommended | ₹10.00 L | — | 0% | 25.2 | LOW |
| Providing the New Shuttering arrangements to the Vent No.04 100% similarity with another nearby work | NAGAPATTINAM(DISTRICT COLLECTOR NAGAPATTINAM_4) | Recommended | ₹10.00 L | — | 0% | 25.2 | LOW |
| CONSTRUCTION OF KALAIYARANGAM NEAR SRI THROWBATHY AMMAN TEMP 84 days beyond expected completion | NAGAPATTINAM(DISTRICT COLLECTOR NAGAPATTINAM_4) | Recommended | ₹12.00 L | 84 d | 0% | 24.2 | LOW |
| PROVIDING BT ROAD FOR CHINNA VADAKU VELI SALAI AT THIRUKUVAL 84 days beyond expected completion | NAGAPATTINAM(DISTRICT COLLECTOR NAGAPATTINAM_4) | Recommended | ₹10.00 L | 84 d | 0% | 22.9 | LOW |
| Construction of Two Wheeler Shed to Govt High School at VAZH 84 days beyond expected completion | NAGAPATTINAM(DISTRICT COLLECTOR NAGAPATTINAM_4) | Recommended | ₹10.00 L | 84 d | 0% | 22.9 | LOW |
| PROVIDING BT ROAD FOR VELAN STREET AT SEMBIYAVELUR OF NATHAP 84 days beyond expected completion | NAGAPATTINAM(DISTRICT COLLECTOR NAGAPATTINAM_4) | Recommended | ₹9.50 L | 84 d | -5% | 22.8 | LOW |