Open this link on a larger screen to see the verification queue.
103 works across 1 implementing agency, recommended by 1 member of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Mayiladuthurai(District Collector Mayiladuthurai_IDA) | 103 | 10 | ₹6.45 Cr | 11 | 19.5 | SRI SAI ENTERPRISES 25% of spend · 14 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Sudha R MAYILADUTHURAI | 103 | ₹6.45 Cr | 11 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Education | 38 | ₹1.40 Cr | 7 |
| Street Lighting | 30 | ₹2.54 Cr | 1 |
| Community Buildings | 22 | ₹1.74 Cr | 3 |
| Religious & Cultural | 9 | ₹39.99 L | 0 |
| Roads & Paving | 3 | ₹20.50 L | 0 |
| Water | 1 | ₹16.75 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Procurment of furniture at Govt. girls Highr Seceondry Scho ₹500,000 against a ₹235,000 median for Education works in MAYILADUTHURAI (113% above, 49 peer works) | Mayiladuthurai(District Collector Mayiladuthurai_IDA) | Recommended | ₹5.00 L | 190 d | +113% | 59.0 | MEDIUM |
| Procurment of furniture at Govt. Girls Highr Seceondry Scho ₹800,000 against a ₹235,000 median for Education works in MAYILADUTHURAI (240% above, 49 peer works) | Mayiladuthurai(District Collector Mayiladuthurai_IDA) | Recommended | ₹8.00 L | 190 d | +240% | 56.0 | MEDIUM |
| Procurment of furniture at Govt. Boys Highr Seceondry Schoo ₹800,000 against a ₹235,000 median for Education works in MAYILADUTHURAI (240% above, 49 peer works) | Mayiladuthurai(District Collector Mayiladuthurai_IDA) | Recommended | ₹8.00 L | 190 d | +240% | 56.0 | MEDIUM |
| Procurment of furniture at Govt. Highr Seceondry School in ₹500,000 against a ₹235,000 median for Education works in MAYILADUTHURAI (113% above, 49 peer works) | Mayiladuthurai(District Collector Mayiladuthurai_IDA) | Recommended | ₹5.00 L | 190 d | +113% | 56.0 | MEDIUM |
| Construction of Cremation Shed at 6th ward Near Kaveri Kara ₹1,600,000 against a ₹750,000 median for Community Buildings works in MAYILADUTHURAI (113% above, 57 peer works) | Mayiladuthurai(District Collector Mayiladuthurai_IDA) | Recommended | ₹16.00 L | 230 d | +113% | 56.0 | MEDIUM |
| Construction of Cremation Shed at Madavamedu in Puthupattina 230 days beyond expected completion | Mayiladuthurai(District Collector Mayiladuthurai_IDA) | Recommended | ₹6.00 L | 230 d | -20% | 54.0 | MEDIUM |
| Procurment of furniture at Govt. Girls Highr Seceondry Scho ₹400,000 against a ₹235,000 median for Education works in MAYILADUTHURAI (70% above, 49 peer works) | Mayiladuthurai(District Collector Mayiladuthurai_IDA) | Recommended | ₹4.00 L | 190 d | +70% | 51.6 | MEDIUM |
| Procurement of Furniture at Govt. Higher Secondary School in ₹850,000 against a ₹235,000 median for Education works in MAYILADUTHURAI (262% above, 49 peer works) | Mayiladuthurai(District Collector Mayiladuthurai_IDA) | Recommended | ₹8.50 L | — | +262% | 45.7 | MEDIUM |
| Procurement of Furniture at Govt. Higher Secondary School ₹850,000 against a ₹235,000 median for Education works in MAYILADUTHURAI (262% above, 49 peer works) | Mayiladuthurai(District Collector Mayiladuthurai_IDA) | Recommended | ₹8.50 L | — | +262% | 42.7 | MEDIUM |
| Construction of Bus Shelter at Thillaividangan in Madhanam P 231 days beyond expected completion | Mayiladuthurai(District Collector Mayiladuthurai_IDA) | Recommended | ₹7.00 L | 231 d | -7% | 40.0 | MEDIUM |
| Installation of High mass Light at Bazaar in Kesingan Pancha 231 days beyond expected completion | Mayiladuthurai(District Collector Mayiladuthurai_IDA) | Recommended | ₹7.00 L | 231 d | -22% | 40.0 | MEDIUM |
| Construction of Cremation Shed at 2nd ward Vaithiyampettai V 230 days beyond expected completion | Mayiladuthurai(District Collector Mayiladuthurai_IDA) | Recommended | ₹7.00 L | 230 d | -7% | 40.0 | LOW |
| Installation of High mass Light at A.Sathanoor in Eduthukatt 230 days beyond expected completion | Mayiladuthurai(District Collector Mayiladuthurai_IDA) | Recommended | ₹7.00 L | 230 d | -22% | 40.0 | LOW |
| Installation of High mass Light near Sri Subramaniya Samy Th 230 days beyond expected completion | Mayiladuthurai(District Collector Mayiladuthurai_IDA) | Recommended | ₹7.00 L | 230 d | -22% | 40.0 | LOW |
| Installation of High mass Light near Pillaiyarkoil in Mandha 230 days beyond expected completion | Mayiladuthurai(District Collector Mayiladuthurai_IDA) | Recommended | ₹7.00 L | 230 d | -22% | 40.0 | LOW |