Open this link on a larger screen to see the verification queue.
76 works across 1 implementing agency, recommended by 2 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Shahpura(DISTRICT COLLECTOR Shahpura_IDA) 1 high risk | 76 | 40 | ₹3.46 Cr | 4 | 24.2 | C S TECHNOLOGIES 11% of spend · 362 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Damodar Agrawal BHILWARA | 75 | ₹3.21 Cr | 3 |
| Pramod Tiwari Sitting Rajya Sabha | 1 | ₹25.00 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Community Buildings | 35 | ₹1.99 Cr | 1 |
| Street Lighting | 19 | ₹39.73 L | 3 |
| Roads & Paving | 11 | ₹52.87 L | 0 |
| Religious & Cultural | 6 | ₹29.71 L | 0 |
| Education | 2 | ₹10.00 L | 0 |
| Water | 2 | ₹9.70 L | 0 |
| Sports | 1 | ₹5.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| 1. For construction of 1 community building in Nohre of Chha ₹2,500,000 against a ₹500,000 median for Community Buildings works in SHAHPURA (400% above, 45 peer works) | Shahpura(DISTRICT COLLECTOR Shahpura_IDA) | Recommended | ₹25.00 L | 437 d | +400% | 76.9 | HIGH |
| SITC of 10 Mtr Highmast with 180 watt Light with complete wi 114 days beyond expected completion | Shahpura(DISTRICT COLLECTOR Shahpura_IDA) | Recommended | ₹2.15 L | 114 d | +3% | 44.7 | MEDIUM |
| SITC of 10 Mtr Highmast with 180 watt Light with complete wi 113 days beyond expected completion | Shahpura(DISTRICT COLLECTOR Shahpura_IDA) | Recommended | ₹2.15 L | 113 d | +3% | 43.0 | MEDIUM |
| SITC of 10 Mtr Highmast with 180 watt Light with complete wi 114 days beyond expected completion | Shahpura(DISTRICT COLLECTOR Shahpura_IDA) | Recommended | ₹2.15 L | 114 d | +3% | 42.1 | MEDIUM |
| SITC of 10 Mtr Highmast with 180 watt Light with complete wi 114 days beyond expected completion | Shahpura(DISTRICT COLLECTOR Shahpura_IDA) | Recommended | ₹2.15 L | 114 d | +3% | 39.8 | LOW |
| Samudayik Bhawan nirman kary Devnarayan Mandir ke pas Eitmar 248 days beyond expected completion | Shahpura(DISTRICT COLLECTOR Shahpura_IDA) | Recommended | ₹5.00 L | 248 d | 0% | 39.6 | LOW |
| 1.RAMLAL KHAROL ke makan ke paas visrantigrah nirman Vill- S 248 days beyond expected completion | Shahpura(DISTRICT COLLECTOR Shahpura_IDA) | Recommended | ₹5.00 L | 248 d | 0% | 39.6 | LOW |
| Sagas Ji ke sthan ke pas kabutarkhana nirman kary Vill-Baner 203 days beyond expected completion | Shahpura(DISTRICT COLLECTOR Shahpura_IDA) | Recommended | ₹5.00 L | 203 d | +2% | 38.9 | LOW |
| Bheel Basti me SAMUDAYIK BHAWAN Nirman Vill- Dodwaniyo Ka Kh 203 days beyond expected completion | Shahpura(DISTRICT COLLECTOR Shahpura_IDA) | Recommended | ₹5.00 L | 203 d | 0% | 38.9 | LOW |
| DAYAL GIRI ke Ghar ke Saamane VISRANTI GRAH nirman Vill- Dab 203 days beyond expected completion | Shahpura(DISTRICT COLLECTOR Shahpura_IDA) | Recommended | ₹5.00 L | 203 d | +2% | 38.9 | LOW |
| Khatiko Ke Mohalle me Samudayik Bhawan Nirman Kary Vill-Dham 203 days beyond expected completion | Shahpura(DISTRICT COLLECTOR Shahpura_IDA) | Recommended | ₹5.00 L | 203 d | 0% | 38.9 | LOW |
| CC Sadak may nali nirman kary MALI MOHLLA Vill-Akola GP-Akol 176 days beyond expected completion | Shahpura(DISTRICT COLLECTOR Shahpura_IDA) | Recommended | ₹5.00 L | 176 d | +0% | 37.6 | LOW |
| sarvjanik samudayik bhawan vistar kary teli samaj mohlla pip 176 days beyond expected completion | Shahpura(DISTRICT COLLECTOR Shahpura_IDA) | Recommended | ₹5.00 L | 176 d | 0% | 37.6 | LOW |
| samudayik bhawan vistar kary gopal putra bhoja gurjar ke mak 176 days beyond expected completion | Shahpura(DISTRICT COLLECTOR Shahpura_IDA) | Recommended | ₹5.00 L | 176 d | 0% | 37.6 | LOW |
| Sanskratik gatividhiyo hetu Bhawan Nirman kary SEN SAMAJ ke 166 days beyond expected completion | Shahpura(DISTRICT COLLECTOR Shahpura_IDA) | Recommended | ₹5.00 L | 166 d | 0% | 36.2 | LOW |