Open this link on a larger screen to see the verification queue.
32 works across 1 implementing agency, recommended by 6 members of parliament. No allocation figure is published per district — every rupee below is summed from the works themselves.
The people a district authority actually supervises. Vendor concentration is counted from the payment records: an agency paying almost everything to one vendor is worth a question, not an accusation.
| # | Agency | Works | Completed | Sanctioned | To verify | Avg score | Top vendor |
|---|---|---|---|---|---|---|---|
| 1 | Neem Ka Thana(DISTRICT COLLECTOR Neem Ka Thana_IDA) | 32 | 11 | ₹1.80 Cr | 17 | 36.5 | GRAM PANCHAYAT DAYAL KI NANGAL 21% of spend · 80 vendors |
Whose funds paid for this district’s works.
| Member | Works | Sanctioned | To verify |
|---|---|---|---|
| Amra Ram SIKAR | 11 | ₹61.47 L | 4 |
| Brijendra Singh Ola JHUNJHUNU | 11 | ₹54.13 L | 6 |
| Sonia Gandhi Sitting Rajya Sabha | 5 | ₹35.38 L | 4 |
| Randeep Singh Surjewala Sitting Rajya Sabha | 2 | ₹12.67 L | 1 |
| Mukul Wasnik Sitting Rajya Sabha | 2 | ₹12.37 L | 1 |
| Madan Rathore Sitting Rajya Sabha | 1 | ₹3.48 L | 1 |
Sector read from each work’s description.
| Sector | Works | Sanctioned | To verify |
|---|---|---|---|
| Roads & Paving | 12 | ₹68.89 L | 6 |
| Water | 8 | ₹41.15 L | 4 |
| Education | 7 | ₹41.98 L | 5 |
| Community Buildings | 4 | ₹21.48 L | 2 |
| Boundary & Protection | 1 | ₹6.00 L | 0 |
Ranked by score. Cost is judged against comparable works in this district and sector, so a high cost score means unlike its neighbours — not overpriced.
| Work | Agency | Status | Sanctioned | Delay | Cost vs peers | Score | Band |
|---|---|---|---|---|---|---|---|
| Construction of Boundary Wall at Rajkiya Uchhatar Madhyamik ₹1,000,000 against a ₹549,242 median for Education works in NEEM KA THANA (82% above, 8 peer works) | Neem Ka Thana(DISTRICT COLLECTOR Neem Ka Thana_IDA) | Recommended | ₹10.00 L | 142 d | +82% | 68.6 | MEDIUM |
| Installation of a 200 mm three-phase tube well with electric 240 days beyond expected completion | Neem Ka Thana(DISTRICT COLLECTOR Neem Ka Thana_IDA) | Recommended | ₹7.00 L | 240 d | +40% | 63.4 | MEDIUM |
| Construction of Interlocking kharanja road at Dhani Babariya 376 days beyond expected completion | Neem Ka Thana(DISTRICT COLLECTOR Neem Ka Thana_IDA) | Recommended | ₹6.00 L | 376 d | 0% | 63.4 | MEDIUM |
| Installation of a single-phase tube well with electrical con 240 days beyond expected completion | Neem Ka Thana(DISTRICT COLLECTOR Neem Ka Thana_IDA) | Recommended | ₹5.00 L | 240 d | 0% | 61.1 | MEDIUM |
| public bus stand construction work 174 days beyond expected completion | Neem Ka Thana(DISTRICT COLLECTOR Neem Ka Thana_IDA) | Recommended | ₹3.48 L | 174 d | 0% | 59.0 | MEDIUM |
| Construction of CC Road Interlocking Road at near from Daani ₹848,542 against a ₹599,522 median for Roads & Paving works in NEEM KA THANA (42% above, 19 peer works) | Neem Ka Thana(DISTRICT COLLECTOR Neem Ka Thana_IDA) | Recommended | ₹8.49 L | 142 d | +42% | 58.5 | MEDIUM |
| Construction Rest House SC mohalla Thoi 197 days beyond expected completion | Neem Ka Thana(DISTRICT COLLECTOR Neem Ka Thana_IDA) | Recommended | ₹7.00 L | 197 d | 0% | 42.0 | MEDIUM |
| construction of interlock road from home of Rohtas towards h 267 days beyond expected completion | Neem Ka Thana(DISTRICT COLLECTOR Neem Ka Thana_IDA) | Recommended | ₹5.00 L | 267 d | -17% | 41.4 | MEDIUM |
| Construction of gravel road from main road to Dhani Nakhri.
273 days beyond expected completion | Neem Ka Thana(DISTRICT COLLECTOR Neem Ka Thana_IDA) | Recommended | ₹5.00 L | 273 d | -17% | 41.4 | MEDIUM |
| Construction of interlock road from main road towards Ashlaw 273 days beyond expected completion | Neem Ka Thana(DISTRICT COLLECTOR Neem Ka Thana_IDA) | Recommended | ₹5.00 L | 273 d | -17% | 41.4 | MEDIUM |
| construction of tin shed in sarv samaj shamshan behind water 273 days beyond expected completion | Neem Ka Thana(DISTRICT COLLECTOR Neem Ka Thana_IDA) | Recommended | ₹5.00 L | 273 d | 0% | 41.4 | MEDIUM |
| construction of nala in rajkiya uch madhyamik vidyalaya in m 273 days beyond expected completion | Neem Ka Thana(DISTRICT COLLECTOR Neem Ka Thana_IDA) | Recommended | ₹5.00 L | 273 d | -9% | 41.4 | MEDIUM |
| construction of sewerage pipeline and drain from house of Ba 273 days beyond expected completion | Neem Ka Thana(DISTRICT COLLECTOR Neem Ka Thana_IDA) | Recommended | ₹5.00 L | 273 d | 0% | 41.4 | MEDIUM |
| Tinshed construction work at prayer Govt Sanskrit Upadhyay v 197 days beyond expected completion | Neem Ka Thana(DISTRICT COLLECTOR Neem Ka Thana_IDA) | Recommended | ₹6.00 L | 197 d | +9% | 41.3 | MEDIUM |
| Class room construction work in Mahatma Gandhi Government Sc 257 days beyond expected completion | Neem Ka Thana(DISTRICT COLLECTOR Neem Ka Thana_IDA) | Recommended | ₹5.00 L | 257 d | -9% | 41.3 | MEDIUM |